Pacy & Wheatley | Healthcare Design and Build, Huddersfield

Healthcare Design and Build, Huddersfield

Client: Horizon Healthcare
Type: Design & Build / New Build
Location: Longhill Road, Huddersfield
Sector: Private Healthcare
Procurement Method: Tendered
Project Value: c £700,000



Project Description

Pacy and Wheatley are pleased to be appointed for a design and build project, a new quality home for Huddersfield to provide specialist residential care. The project consists of the construction of a new 8 bed timber frame/stone faced care home on the site of a former Methodist church. Facilities are to include a sensory activity room, all en-suite rooms, an assisted bathroom, on site staff accommodation and laundry / kitchen installations. External works including new gas, water and electric services, a new car park and sewer connections are being successfully co-ordinated to ensure minimal disruption to the residents on the street. The end product is sure to be an attractive, well finished and beautifully landscaped building.

The Challenge

The site is on a busy residential road and in close proximity to a busy supermarket. Consideration has to be given to civil works by close liaison with the highways authority and council. Significant site remodelling and shaping has been undertaken to allow the foundation & slab installation.

Wednesday, 18 January 2017

Pacy & Wheatley | Commercial Construction Company

Commercial Construction Company
Pacy and Wheatley are an experienced construction company covering a wide variety of commercial and industrial construction services. As skilled building contractors, we are committed to the delivery of highly varied complex projects. We assist our customers in keeping abreast of fast-paced and ever changing technologies. With commercial construction projects ranging from 4 story office blocks to warehousing and manufacturing facilities we have developed a broad portfolio in this exacting area of the construction industry, meeting the needs of today's demand for functional and well designed premises.
A sample selection of commercial construction projects successfully completed within this sector, but not limited to, include 4 storey NHS office accommodation in Sheffield, manufacturing facilities for a leading UK hydraulics company, manufacturing facilities and offices for a Yorkshire based structural steelwork contractor, storage and distribution facilities for a Doncaster based transport company, and a specialist high security archives unit for west Yorkshire Joint services. Our confidence and experience underline our commitment to partnership and innovative approach, delivering the right results for our clients.
For further information on how we can help with your commercial and industrial construction projects, complete our quick contact form below.


Pacy & Wheatley
Telephone: 01302 760843
E-mail: cwheatley@pacy-wheatley.co.uk

Friday, 9 December 2016

Pacy & Wheatley | Healthcare

Healthcare Construction Company
Pacy and Wheatley, premier Healthcare Construction Company, have a wealth of experience in design, construction and refurbishment of Healthcare buildings. Our portfolio in this arena spans many years and encompasses all aspects of specialist care construction projects. As one of the Uk's leading construction companies, we are wholly customer focused and provide a platform where our team can work with you to achieve your vision. Our continuous improvement culture will guide your project from the design phase to completion, with a flexibility appropriate to your needs.
Pacy and Wheatley's in house project management team, are skilled in all aspects of Healthcare design, construction and refurbishment; that together with excellent supply chain management, ensures delivery of your project on time and on budget. Incorporating a range of innovative systems, modern methods of construction of known quality, cost and process; allows Pacy and Wheatley to effectively deliver optimum Whole Life Cost and Sustainable Solutions.

Healthcare Construction Sectors:

  • Primary Care
  • Residential Care
  • Mental and Physical Health Care
  • Learning Difficulties
  • Care Villages
  • Healthcare Centres

Visit our website www.pacy-wheatley.co.uk
Social Media Managed By Multi-Web-Services

Friday, 18 November 2016

Pacy & Wheatley | Design and Build in Derbyshire




Design and Build in Derbyshire

  • Client:
    Paragon Healthcare
  • Sector:
    Healthcare/design and build.
  • Type:
    Design and Build
  • Procurement Method:
    Tender/Negotiation
  • Location:
    Derbyshire
  • Project Value:
    £870,000


Project Description
Pacy and Wheatley Construction were commissioned on a design and build basis to construct and fit out a timber framed project based on Moorfield Avenue within the historic town of Bolsover, Derbyshire. The facility was 2 storeys and was to have 11 bedrooms with lounges and dining and activity rooms for a high level of care and comfort for its residents. The property had a large rear garden which was to be landscaped to ensure the residents has spacious areas to relax in the beautiful surroundings; the project was to be completed within 24 weeks for the client.

The Challenge
Design co-ordination to ensure the 24-week program was achievable through the design teams finding, we decided that the ground was currently not suitable and require vibropiling which was the chosen method to stabilise this with no effect to adjacent shop and neighbouring properties in close proximity.
The H&S actions required assessment to ensure the public using the pathways to the local school and shop and the neighbourhood residents were as un affect as possible by the works.
Due to the timber framed structure and the low-level area these had to be programmed very carefully as the building could not become water tight until the main roof was complete and scaffold was removed, this could easily cause difficulty with water damage within he timber frame elements of the build.
Long lead time items and services needed constant liaison to ensure the 24 weeks allocated time.
To program the fast track timber frame construction scheme together with sub-contractors to achieve the goal.
Achieve zero incidents throughout the build of the facility whilst works were carried out.
Pulling together the best supply chain to ensure total teak work.
Maintain and build on repeat business client to maintain this to the next project.

Conform to CSCI standards.

The Solution
The design team assembled at an early time with contract programmes schedules meeting through this period to ensure the design was buildable and suitable for the client’s needs/requirements.
Vibration monitoring  was utilise to all sides of the property to ensure the shops and other building were not affected
Liaison with neighbours prior to commencement was paramount to ensure continual awareness of the sites presence and task ahead.
The roof was placed which allowed the scaffold to penetrate the low level roof and allowed access to the main roof and gable wall, this was felted and passed under the scaffold upon the main roof completion, this was removed and the roof completed to ensure internal trades could continue.
Health and safety paramount site compound secured with security fencing to ensure no entry to unauthorised persons.
Co-ordinated throughout by ourselves to ensure passing of lengthy lead time information and processing of order within the early design schedule.
In house staff utilised for the project that have a good knowledge of the company and procedures required.
Ensure as much of the underground works were complete to gain time at the rear of the program to ensure a quality project delivery.
Ensure the timer frame design was erected and closed in to any elements as soon as possible to ensure works could continue internally.
The facility opened upon time as we achieved routed into the building which was complete.
Team meetings with supply chain to discuss any areas of slight failings and areas improvement could be made.


Key Achievements
Due to the teams, standard snagging routine we handed over the project with effects.
Completion of a large project on time and to budget with minimal disruption to public and neighbouring properties owners
Revitalised a waste land position into a fantastic looking facility which benefits all the neighbourhood.
Positive comments from all involved
The new fantastic home created achievement knowing Pacy and Wheatley was part of helping to provide someone less fortunate to have a new home
Management process with full cooperation of supply chain achieved zero accidents/near misses.


Wednesday, 28 September 2016

Pacy & Wheatley | Steam and Moorlands Garden Centre Case Study


Retail Leisure Construction, North Yorkshire

  • Client:
    Steam & Moorland Garden Centre
  • Sector:
    Commercial
  • Type:
    New build extension (D&B)
  • Procurement Method:
    Competitive Tender
  • Location:
    Pickering, North Yorkshire
  • Project Value:
    £653k




Description

Pacy and Wheatley, premier  retail construction company based Doncaster, Yorkshire, were delighted to have successfully completed the steam & Moorlands Garden Centre, in Pickering, North Yorkshire.

To construct an infill building linking the 2 existing building of machinery centre and garden centre / café, which formed the current garden centre complex.

The construction was steelframe structure, with traditional masonary façade, cladding and feature curtain walling the North and South elevations.

The ground floor links the machinery sales area and garden centre, with the 1st floor becoming a fantastic restaurant setting.

The Challenges

To produce a first class product for a valued client and to complete the project on time and to budget.

Working in and around the live garden centre, which continued trading for business throughout the build.

Limited access to the south elevation of the build.

To achieve an air permeability pass of 7.5 as the building is linked to 2 older -framed units, which has not been built under current regulations or to air permeability standards.

To open the ground floor sales area for business prior to completion of the 1st floor to hit early spring sales.


The Solutions

Utilising competent in house staff and key supply chain members for the project.

Close and daily liaison with the client and staff.

Projected delivery assisted by the use of local labour, suppliers and subcontranctors.

Sub contract collaboration meetings were vital at finishing stage.

Key Achievements

Achieving air permeability of 7.4.

Establishing early relationships with the client and garden centre staff.

Achieving ‘doors open for business’ to the ground floor sales areas in time for early spring sales.

Completion of a fantastic, but huge cantilevered balcony to the length of the south elevation, extending the restaurant to the outside, with elevated views over the garden centre.



Wednesday, 31 August 2016

Pacy & Wheatley | Interior Fit Out Contractors



Interior Fit Out Contractors

Pacy and Wheatley Construction, specialist interior fit out contractors, have a vast and diverse experience in the interior refurbishment and fit out sector. Working nationally, our team creates real value for clients through their expertise and wealth of experience helping to make businesses succeed. Offering professional interior refurbishments and remodelling within the Commercial, Retail, Leisure, Healthcare and Education sectors. Pacy and Wheatley operate as the principle contractor, managing all on-site phases of any project in partnership with our clients and their professional team; our robust systems and processes achieve predictable, high quality results.
Pacy and Wheatley have significant experience from the renovation and refurbishment of grade 2 listed buildings, to more modern concepts encompassing Offices, Educational, Healthcare, Commercial and Retail schemes. For further information on how we can help with your interior refurbishments, complete the quick contact form below.



Wednesday, 20 July 2016

Pacy & Wheatley | Accident Statistics



Pacy and Wheatley Construction accident statistics are calculated in line with HSE methodology. i.e. accidents per 100,000 working hours and presented annually in April. These are then compared with the latest year's HSE statistics.
Significant improvements were made in 2012 as follows:
  • Safety
  • Environmental - ISO 14001
  • The number of all accidents on sites has reduced and we have again achieved a significantly lower accident incident rate than the nationals average